AD 2016-24-08 Airworthiness Directives; Rolls-Royce plc Turbofan Engines

Superseded. This directive was replaced by AD 2020-25-04. Work to the current one.
2017-01-05
2016-12-01
39-18725
FAA-2016-6692
Engine
2020-25-04

Applicability*9

This AD applies to Rolls-Royce plc (RR) RB211-Trent 875-17, RB211-Trent 877-17, RB211-Trent 884-17, RB211-Trent 884B-17, RB211-Trent 892-17, RB211-Trent 892B-17, and RB211-Trent 895-17 turbofan engines.

Compliance

For the purpose of this AD, a “shop visit” is defined as induction of an engine into the shop for maintenance involving the separation of pairs of major mating engine flanges, except that the separation of engine flanges solely for the purposes of transportation without subsequent engine maintenance does not constitute an engine shop visit.

Required actions

The Manager, Engine Certification Office, FAA, may approve AMOCs for this AD. Use the procedures found in 14 CFR 39.19 to make your request. You may email your request to: ANE-AD-AMOC@faa.gov.

Unsafe condition

Comply with this AD within the compliance times specified, unless already done. (1) Within 7,500 engine flight hours (FHs) time since new, or since last inspection, or within 150 flight cycles (FCs) after the effective date of this AD, whichever occurs later, inspect the engine upper bifurcation fairing for cracks or missing material. Use paragraph (e)(3) of this AD to perform the inspections. (2) Repeat the inspection required by this AD within every 7,500 engine FHs time since last inspection. (3) Inspect the engine upper bifurcation fairing as follows. Refer to Figure 1 of RR Alert Non-Modification Service Bulletin (NMSB) RB.211-72-AJ165, dated March 31, 2016, for guidance on upper bifurcation fairing inspection locations. (i) Visually inspect upper bifurcation fairing seal face 22, seal support 23, and zone A for any cracks or material loss on the right side. (A) If fairing seal face 22 is found to have released material, repair or replace the fairing before further flight. (B) If there is a single crack found on fairing seal face 22, shorter than 6 mm, repair or replace the fairing within 100 engine flight cycles, or at the next shop visit, whichever occurs sooner. (C) If there is a single crack, longer than 6 mm, found on fairing seal face 22, repair or replace the fairing within 15 engine FCs or at the next shop visit, whichever occurs sooner. (D) If there are two or more cracks found on fairing seal face 22, replace the fairing within 15 engine FCs or at next shop visit, whichever occurs sooner. (E) If there is any cracking or material loss found on seal support 23, replace the fairing within 15 engine FCs or at next shop visit, whichever occurs sooner. (ii) If the visual inspection required by paragraph (e)(3)(i) of this AD does not detect any crack, fluorescent penetrant inspect zone A. Refer to AMM TASK 70-20-02, Water Washable Fluorescent Penetrant Inspection (Maintenance Process 213), or OMat 632, high sensitivity fluorescent penetrant inspection, for guidance on fluorescent penetrant inspection. (A) If a crack shorter than 6 mm is detected, repair or replace the fairing within 100 engine FCs, or at the next shop visit, whichever occurs sooner. (B) If a crack longer than 6 mm is detected, repair or replace the fairing within 15 engine FCs or at the next shop visit, whichever occurs sooner.

Affected ADs

None.

Read the original on the Federal Register →

You just looked this one up by hand

TrackAD holds all 12,278 of them and matches them against the aircraft you actually look after — airframe, engine, propeller and appliances in one pass — then works out what falls due and when.

Look round a real shop first Start free

The demonstration shop is eleven real aircraft with a year of work behind them. No account needed.

The directive text above is reproduced from the Federal Register, a work of the United States government and in the public domain. The separation into applicability, compliance and required actions is TrackAD's.*1