AD 2025-12-08 Airworthiness Directives; General Electric Company Engines

2025-07-23
2025-06-18
—
—
Engine
—

Applicability*9

This AD applies to the following General Electric Company (GE) Model engines: (1) CF34-8C1, CF34-8C5, CF34-8C5A1, CF34-8C5A2, CF34-8C5A3, and CF34-8C5B1 engines with an installed combustion chamber assembly (CCA) having part number (P/N) 4145T11G08, 4145T11G10, 4180T27G02, 4180T27G04, or 4923T82G02; and (2) CF34-8E2, CF34-8E2A1, CF34-8E5, CF34-8E5A1, CF34-8E5A2, CF34-8E6, and CF34-8E6A1 engines with an installed CCA having P/N 4145T11G08, 4145T11G09, 4180T27G01, or 4180T27G03.

Compliance

Comply with this AD within the compliance times specified, unless already done.

Required actions

(1) For affected Group 1 engines with an installed CCA having less than 15,000 part cycles since new (PCSN) as of the effective date of this AD, before the accumulation of 28,500 PCSN, remove the CCA from service and replace with P/N 4180T27G08 or a later approved P/N. (2) For affected Group 2 engines with an installed CCA having less than 15,000 PCSN as of the effective date of this AD, before the accumulation of 25,500 PCSN, remove the CCA from service and replace with P/N 4180T27G07 or a later approved P/N. (3) For affected Group 1 and 2 engines with an installed CCA having between 15,000 PCSN and 24,999 PCSN as of the effective date of this AD, before the accumulation of 25,000 PCSN, perform a fluorescent penetrant inspection (FPI) on the forward flange of the CCA for any indications. (4) If no indications are found during the FPI required by paragraph (g)(3) of this AD, within 15,000 part cycles from the date of the FPI, remove the CCA from service and replace with P/N 4180T27G07, 4180T27G08, or a later approved P/N, as applicable. Multiple FPIs of the forward flange prior to the 25,000 PCSN threshold are permitted. However, the affected CCA must be removed from service and replaced no later than 15,000 cycles from the last inspection performed before the 25,000 PCSN threshold. (5) For affected Group 1 and 2 engines with an installed CCA having more than 25,000 PCSN as of the effective date of this AD, at the next engine shop visit after the effective date of this AD, perform an FPI on the forward flange of the CCA for any indications. (6) If no indications are found during the FPI required by paragraph (g)(5) of this AD, within 15,000 part cycles from the date of the FPI and not to exceed 41,100 PCSN, remove the CCA from service and replace with P/N 4180T27G07, 4180T27G08, or a later approved P/N, as applicable. (7) If an indication is found during any FPI required by paragraph (g)(3) or (5) of this AD, before further flight, remove the CCA from service and replace with P/N 4180T27G07, P/N 4180T27G08, or a later approved P/N, as applicable.

Unsafe condition

This AD was prompted by a predicted reduction in the cyclic life of the CCA forward flange. The FAA is issuing this AD to prevent failure of the CCA. The unsafe condition, if not addressed, could result in failure of the CCA before reaching the published life limit, uncontained release of the CCA, damage to the engine, and damage to the airplane.

Affected ADs

None.

Read the original on the Federal Register →

You just looked this one up by hand

TrackAD holds all 12,278 of them and matches them against the aircraft you actually look after — airframe, engine, propeller and appliances in one pass — then works out what falls due and when.

Look round a real shop first Start free

The demonstration shop is eleven real aircraft with a year of work behind them. No account needed.

The directive text above is reproduced from the Federal Register, a work of the United States government and in the public domain. The separation into applicability, compliance and required actions is TrackAD's.*1